
Bangladesh
At the time of partition of India in the year 1947, Power Generation and distribution of this part of the country (present Bangladesh) was in the hands of some private companies.
The power supply to 17 districts was within the township in a limited way. Power used to be supplied to most of the district during the night time only and the supply voltage was 400 volts. Only exception was Dhaka City where power used to be supplied by 2 Nos. of 1500 KW generators and the generation voltage was 6.6 KV and this was the highest distribution voltage. Besides, power used to be generated by some industries and railway workshops. With all these the total power generation capacity in the country was 21 MW. The generation capacity of the power utility companies together was only 7 MW and there was no transmission system.
Electricity Directorate was created in the year 1948 in order to plan and develop power supply situation of the country. After the creation of Water and Power Development Authority (WAPDA) in the year 1959 Electricity Directorate was merged with WAPDA in 1960. After that it started working as a statutory organization. During, the War of Liberation WAPDA was bifurcated into two autonomous Boards under an Ordinance (P.O. 59 of 1972). East Pakistan’s WAPDA was rechristened as Bangladesh Power Development Board (BPDB) and was solely entrusted with responsibility of Power Generation, Transmission and Distribution of electricity throughout the country. However, during the War of Liberation, power installations suffered extensive damage. As a result, at the worst case, peak demand dropped to 30 MW from the pre-liberation level of 225 MW. So, after independence the immediate problem facing Bangladesh was of rehabilitating the marginalized power supply.
By the end of 1972-73, a rehabilitation and development programme was undertaken in the First Five Year Plan. However, due to the shortage of funds the programme was carried over to the Two Year Plan. Several projects, initiated before the Liberation War was completed and a number of new projects were undertaken during this period. As a result, installed generation capacity increased to 822 MW from 545 MW, while the peak demand rose to 462 MW from 222 MW. However, during this period the power sector was marked with the operational issues, as a result the operational capacity remained much lower. (Source: http://www.sdnbd.org/)
Further, to reduce the gap between demand and generation capacity, the Second Plan undertook a rapid expansion programme. The most important achievement during this period was the construction of the East-West electrical inter-connector which enabled the transfer of gas-based low cost power from the east to the west. Five power generation plants having a total installed capacity of 330 MW were completed during this period. But generation capacity still lagged behind the demand. The main constraint to the expansion of power supply was shortfall of resources coupled with a huge system loss and a slow response to tariff adjustment against rising fuel cost. By the end of the Second Plan, the system loss stood at 37.5 per cent. An investment programme of Tk. 14,370 million at 1979/80 price was undertaken. The Second Plan also pursued a policy of substituting imported fuel by natural gas. A significant progress was made in this direction. By the end of 1984/85, total number of electricity consumers stood at about 964,000 compared with 522,000 in 1979/80. Table shows the progress of power development in the country during 1972-96.
Power sector development in Bangladesh from 1972-96
Items |
1972 |
1973 |
1975 |
1980 |
1985 |
1990 |
1995 |
1996 |
Installed Capacity (MW) |
550 |
608 |
752 |
822 |
1,141 |
2,352 |
2,908 |
2,908 |
Effective Generation (MW) |
469 |
455 |
557 |
625 |
1,018 |
1,834 |
2,133 |
2,105 |
Maximum Demand (MW) |
183 |
222 |
396 |
462 |
887 |
1,509 |
1,970 |
2,087 |
230 kV Transmission Line (Km) |
- |
- |
- |
- |
179 |
250 |
419 |
419 |
132 kV Transmission Line (Km) |
828 |
828 |
1,395 |
1596 |
1,971 |
2,235 |
2,469 |
3,017 |
66 kV Transmission Line (Km) |
167 |
167 |
167 |
167 |
167 |
167 |
167 |
167 |
Distribution Line(Km) (33 kv & below) |
9,010 |
9,686 |
17,003 |
20,256 |
34,796 |
69,731 |
103,540 |
121,817 |
No. of Consumers |
254,584 |
277,884 |
403,518 |
529,660 |
848,152 |
1,670,137 |
2,766,765 |
3,090,829 |
Per Capita Generation (kwh) |
- |
15.6 |
22.9 |
27 |
46 |
70 |
92 |
95 |
Ensuring supply ahead of demand is the ideal situation in case of electricity for meeting manufacturing, irrigation, commercial and domestic needs of any economy. However, it was not possible to do so in Bangladesh. Against a peak demand of 1640 MW in 1990/91 and 1970 MW in 1994/95, the installed capacity was only 2352 MW and 2908 MW respectively. The operational capacity (2133 MW) was again interrupted by occasional power outages owing to fluctuations in gas pressure, transmission and distribution faults. These caused enormous losses to industrial production and commercial activities. However, Irrigation suffered relatively less due to its use of diesel power and electricity supplied by REB in off-peak hours.
Electricity generation, transmission and distribution require large financial investment. Besides Bangladesh having considerable gas reserve and promising potentials, however due to high system loss, large account receivables, poor management, inability to rationalize tariff rate and delay in introduction of reforms the concessional loans for the power sector from the multilateral development partners was not made available in the Fourth Plan period. The Fourth Plan was formulated with a public sector allocation of Tk. 64,500 million at 1989/90 prices for the power sector. This allocation was inadequate in relation to the physical targets set in the Plan document. Due to shortage of both local and external resources, the Plan allocation as well as Plan targets had to be revised. The revised allocation was Tk. 45,360 million at 1989/90 price level. Consequently, needed investments for generation, transmission and distribution of electricity could not be made during 1990-95. Hard term suppliers' credit and inadequate government resources made it possible to add only about 581 MW of generation capacity in the following power plants during the Fourth Plan Period.
However, due to non-completion of scheduled rehabilitation of some power stations, generation capability decreased by 271 MW and about 11 MW capability was retired during the period. The net capacity increase was thus 299 MW. In addition, reduced gas supply caused shut-down of some power stations resulting in lower operational supply of electricity. Major targets as well as the achievements during the Plan period are shown in the table below.
Target and achievement of Fourth five year plan
Agency |
Particulars |
Actual |
Fourth Plan |
Achievement |
Cumulative Position in (1994-95) |
Position in 1989/90 |
Target |
New Addition during Fourth Plan (1990-95) |
|||
BPDB |
Installed Capacity (MW) Consumer connection (No.) |
2352 4150 30256 (Excluding DESA) 850,438 |
2878 2621 36734
1,050,000 |
581 2369 4437
225,296 |
*2908 6519 34693
1,075,734 |
REB |
Distribution line km |
35333 |
61188 |
29853 |
65186 |
DESA |
Transmission line (km) 132 kv |
221 433 |
- - |
104 874 |
325 1307 |
* 2352 MW + 581 MW new – 25 MW retired/standby = 2908 MW
** 1834 MW + 581 MW new – 11 MW retired – 271 MW derated/decrease for maintenance & rehabilitation = 2133 MW
During late 1990s reforms were initiated with organizational changes being made in the area of transmission and distribution of power in the country with Bangladesh Power Development Board (BPDB) being entrusted with generation, transmission and distribution in urban areas. Dhaka Electric Supply Authority (DESA) under the DESA Act as amended in 1998 was restructured into a corporate body with an independent Board of Directors. DESA was mandated with distribution of electricity in the Greater Dhaka area and Rural Electrification Board (REB) undertaking distribution in the rural areas. As a result outlaying areas outside metropolitan Dhaka with 4,100 km of assets was transferred to REB. This transfer resulted in an increase in demand of 8 Palli Bidyut Samities (PBSs) around Dhaka from 110 MW in FY 1997 to 575 MW in FY 2003 and also resulted in system loss reduction.
Power generation and distribution was opened to both local and foreign private investments with the formulation of "The Private Sector Power Generation Policy" in 1996. A Rural Power Company (RPC) was set up for generation and supply of power exclusively to the REB. Dhaka Electric Supply Company Limited (DESCO) was incorporated in November 1996 with ultimate objective of taking over all assets from DESA. DESCO commenced commercial operation from 1 September 1998 by taking over Mirpur area from DESA. DESCO has a fully independent board and introduced commercially oriented business culture with new service rules. DESCO has succeeded in reducing system loss from 43% at the time of taking over to 19% in June 2003. Billing and collections have substantially improved.
Power Grid Company Limited of Bangladesh (PGCB) was incorporated on 21 November 1996 to take over entire transmission assets of BPDB and DESA by December 2002. PGCB has taken over 100 percent of transmission assets from BPDP. Transmission assets of DESA (other than those that form integral part of DESA operation) have also been handed over to PGCB by December 2002. PGCB is fully responsible for construction of all new transmission assets.
Power Division was established in 1998 under the Ministry of Power, Energy and Mineral Resources vide Cabinet Division Notification No. CD-4/1/94-Rules/23(100), dated 25 March 1998. It is entrusted with the responsibility of overall management of the power sector in Bangladesh. Further, ‘Power Cell’ has been created by the government under Power Division, Ministry of Power, and Energy & Mineral Resources under “TA for Implementation of Bangladesh power sector reform” project to carry forward the Power Sector reform activities of the government of Bangladesh.
Power Cell drafted Electricity Reform Bill with assistance from both World Bank and Asian Development Bank. The Cabinet approved draft of the bill in 2000, and again in 2002. Of late, the Government decided to enact a single bill entitled ‘Energy Regulatory Commission Bill’ to cover electricity, gas and oil sectors. Integrated bill was cleared by the parliament on 10 March 2003 and led to the formulation of Bangladesh Electricity Regulatory Commission.
In Bangladesh, 90 million of the population out of 140 million does not have direct access to electricity and remaining 50 million people have access but reliable and quality power is still beyond their reach. The installed generation capacity has grown to 5269 MW (as on June 2007) from a meager 88 MW in 1960. Electricity generation grew at about 7% p. a. during last fifteen years compared with average annual GDP growth rate of about 5.5%. Table below gives detail of net generation, sales, losses and customer number.
Trends in net generation, sales, losses and customer numbers (2002-2007)
Description |
2002 |
2003 |
2004 |
2005 |
2006 |
2007 (June 07) |
Electricity sent out (GWh) |
17445 |
18,422 |
20302 |
21408 |
22978 |
23267 |
Growth in Electricity sent out |
7.30% |
5.60% |
10.20% |
5.40% |
7.30% |
1.30% |
Transmission loss |
3.80% |
3.80% |
3.50% |
3.60% |
3.50% |
3.50% |
Distribution loss |
24.50% |
22.30% |
21.30% |
20% |
19.20% |
18.80% |
Electricity sales (GWh) |
15243.00% |
16332 |
18024 |
19122 |
20836 |
20900 |
Growth in electricity sales |
8.90% |
7.10% |
10.40% |
6.10% |
9% |
0.30% |
Average number of customers (,000s) |
7000.00% |
7700 |
8405 |
9076 |
9800 |
10500 |
Notwithstanding the progress made to date, Bangladesh's per capita electricity generation of 165 kWh p.a. is still among the lowest in the world. About 43% of the population has access to electricity, which is also low compared to many developing countries. This implies that there is scope for significant growth in power sector. Given the huge investment requirement for power development in the country, Bangladesh would be looking forward to various sources of finance. The table below depicts power sector at a glance.
Power Sector at a glance (As on June 2007)
Generation |
|
Installed Capacity |
|
(a) BPDB |
3,872 MW |
(b) IPP & Mixed Sector Total |
1,397 MW |
Total |
5,269 MW |
Maximum Demand Served |
|
Total |
3,785 MW |
Net Energy Generation |
23,267 MkWh |
|
|
Transmission |
|
Transmission Line |
|
230 kV |
1,467 Ckt km |
132 kV |
5,578 Ckt km |
Total |
7,044 Ckt km |
Capacity of Grid S/S |
|
230/132 kV |
5,175 MVA |
132/33 kV |
7,219 MVA |
|
|
Distribution |
|
Distribution Line (33 kV, 11 kV & 0.4 kV) |
2,71,142 km |
Total no. of Consumers |
10.42 Million |
Total no. of Agricultural Consumers |
2 Lac 26 Thousand |
Total no. of Village Electrified |
50,360 |
Access to Electricity |
43% |
Per Capita Generation |
165 kWh |
System Loss (T&D) |
19.30% |
Present Structure of the Power Sector
Owner
• Power Division, Ministry of Power, Energy and Mineral Resources
Generation
• Bangladesh Power Development Board (BPDB)
• Ashuganj Power Station Company, Ltd (APSCL)
• Electricity Generation Company of Bangladesh Ltd. (EGCBL)
• Rural Power Company Ltd. (RPCL)
• Independent Power Producers (IPPs)
Transmission
• Power Grid Company of Bangladesh Ltd. (PGCB)
Distribution
• Bangladesh Power Development Board (BPDB)
• Rural Electrification Board (REB)
• Dhaka Electric Supply Authority (DESA)
• Dhaka Electric Supply Company (DESCO)
• West Zone Power Distribution Co., Ltd. (WZPDCL)
Regulator
• Bangladesh Energy Regulatory Commission
The chart below represents the current Bangladesh power sector structure.
Bangladesh Power Sector: Current Structure
The Government has allocated the following business for the Power Division: -
Power Cell has been created by the government under Power Division, Ministry of Power, Energy and Mineral Resources under “TA for Implementation of Bangladesh power sector reform” project to carry forward the Power Sector reform activities of the government of Bangladesh. The objectives of the reform program can he stated as (not limited to):
Bangladesh Power Development Board (BPDB), established in 1972, is the authority for planning, construction and operation of power generation and transmission facilities throughout Bangladesh and for distribution in urban areas except metropolitan city of Dhaka and its adjoining area. Detail of installed electricity generation capacity has been given in the table below.
Total installed capacity of the BPDB (as on April 2007)
Zone |
Description |
Installed Capacity (MW) |
Derated Capacity (MW) |
Generation (MW) on |
|
Max. |
Min. |
||||
Gen. Day |
Gen. Day |
||||
East Zone Total |
Hydro |
230 |
230 |
100 |
80 |
ST (Steam Turbine) |
2268 |
1935 |
1709 |
1244 |
|
CC (Combined Cycle) |
180 |
132 |
119 |
103 |
|
CT (Combustion Turbine) |
502 |
335 |
152 |
145 |
|
D (Diesel) |
0 |
0 |
0 |
0 |
|
Private |
1060 |
1060 |
999 |
995 |
|
Total East Zone |
4240 |
3692 |
3079 |
2567 |
|
West Zone Total |
ST (Steam Turbine) |
170 |
138 |
60 |
57 |
CT (Combustion Turbine) |
367 |
331 |
200 |
162 |
|
D (Diesel) |
18 |
9 |
7.8 |
6 |
|
Coal |
250 |
250 |
192 |
111 |
|
Private |
200 |
198 |
179 |
179 |
|
Total West Zone |
1005 |
926 |
638.8 |
514.4 |
|
System Total |
Hydro |
230 |
230 |
100 |
80 |
ST (Steam Turbine) |
2438 |
2073 |
1769 |
1301 |
|
CC (Combined Cycle) |
180 |
132 |
119 |
103 |
|
CT (Combustion Turbine) |
869 |
666 |
352 |
307 |
|
D (Diesel) |
18 |
9 |
7.8 |
6 |
|
Coal |
250 |
250 |
192 |
111 |
|
Private |
1260 |
1258 |
1178 |
1174 |
|
Total System |
5245 |
4618 |
3717.8 |
3081 |
|
Ashuganj Power Station Company Ltd. (APSCL) owns the second largest power station in Bangladesh. The installed capacity by its 8 units is 724 MW and present de-rated capacity is 642 MW. Ashuganj Power Station fulfills about 15% of power requirements of the country.
Ashuganj Power Station was established in FY 1966, with the financial assistance of German Government. APSCL had two units, each of 64 MW (Unit 1 & Unit 2) and was commissioned in July 1970. To face the growing requirements for power in the country- Government of Bangladesh decided to setup another two units (Unit 3 & Unit 4) each of 150 MW capacities in Ashuganj. IDA, KfW (Germany), ADB, Kuwait and OPEC provided the financial assistance for this project. After the agreements signing with the contractors, government found that another unit of 150 MW can be established from the left over funds by the donors. With the consent from the donors, Government decided to setup another 150 MW unit (Unit 5).
The work for installation of Unit 3 & 4 was started in 1984 and Unit 5 in 1985. Unit 3, Unit 4 and Unit 5 were commissioned in December 1986, May 1987 and March 1988 respectively. During the planning of installation of Unit 3 & 4 it was decided to install a Combined Cycle Power Plant by financial assistance of British Government. According to that decision, works of two gas turbine units (GT1 & GT2) of 56 MW each and one steam turbine unit (ST1) of capacity 34 MW (with waste heat recovery Boiler) had been started. GT1, GT2 and CCST were commissioned in 1982, 1984 and 1986 respectively.
As a part of the Power Sector Development & Reform Program of Government of Bangladesh (GOB), APSCL has been incorporated under the Companies Act 1994. According to the Articles of Association of the company, 51% of total shares are held by BPDB and the rest 49% is distributed among Ministry of Finance, Ministry of Planning, Power Division, MOPEMR & Energy Division, MOPEMR of GOB.
BPDB has also established a new company, Electricity Generation Company of Bangladesh Ltd (EGCB) to own the Siddhirganj power station (3x120MW). The plant is to be constructed with ADB and WB funding. A coal fired power station (250MW) at Barapukuria, in the north of the country, which is currently under construction.
GOB amended its industrial policy to enable private investment in the power sector. In this regard Private Sector Power Generation Policy was framed in 1996 for promoting private sector participation in the generation of electricity to bridge the gap of competing demands on government resources and declining levels of external assistance from multilateral/bilateral donor agencies.
Power Cell, created under Power Division of Ministry of Power, Energy & Mineral Resources, got the mandate to lead private power development. The Government is strongly committed to attract private investment for installing new power generation capacity on build-own-operate (BOO) basis. Numbers of Fiscal Incentives are provided in the Policy for the private power companies. (A detailed list of the Fiscal and other incentive has been provided in the Appendix I) Under the Private Sector Power Generation Policy, so far 1290 MW power plants have been established and under operation. Moreover 1590 MW plants are planned to be established in near future. List of existing IPPs are stated bellow:
List of existing IPPs
Sl. No. |
Name of Power Plant |
Fuel Type |
Installed Capacity (MW) |
Generation Capacity (MW) |
Date of Com. Opn. |
Contracted Levelized Tariff (US cents/kWh) |
1 |
Khulna Power Company Ltd. (KPCL), Engine Generator |
F. Oil |
110 |
110 |
12/10/1998 |
5.83 (For liquid fuel) 4.40 (For gas) |
2 |
Baghabari, WESTMONT, GT |
Gas |
90 |
90 |
26/06/1999 |
4.31 |
3 |
NEPC Consortium, Gas Generator |
Gas |
110 |
110 |
30/06/1999 |
4.41 |
4 |
Rural Power Co. Ltd. (RPCL), GT |
Gas |
140 |
140 |
14/04/2001 |
4.3 |
5 |
AES, Haripur CC |
Gas |
360 |
360 |
03-06-2001 (SC) 01-12-2001 (CC) |
2.73 * |
6 |
AES, Meghnaghat CC |
Gas |
450 |
450 |
26/11/2002 |
2.79 * |
7 |
Summit Power Co. Ltd. |
Gas |
30 |
30 |
01/10/2003 |
|
|
Total |
|
1290 |
1290 |
|
|
Based on indicative Gas price: 2.40 US$/GJ.
Power Grid Company of Bangladesh (PGCB) was created under the restructuring process of Power Sector in Bangladesh with the objective of bringing about commercial environment including increase in efficiency, establishment of accountability and dynamism. PGCB was incorporated in November 1996 with an authorized capital of Tk.10 billion. It was entrusted with the responsibility to own the national power grid and to operate and expand the same with efficiency. Pursuant to Government decision to transfer of transmission assets to PGCB from Bangladesh Power Development Board (BPDB) and Dhaka Electric Supply Authority (DESA), PGCB has completed taking over of all the transmission assets on 31.12.2003 and operating them.
Earlier generated power of different power plants all over the country was transmitted through PGCB's integrated grid system through 230 kV and 132 kV transmission lines and substations. In 1996 when PGCB was formed, the total length of 230 kV and 132 kV line were 838 ckt km and 4755 ckt km respectively which increases to 1144 ckt km and 4962 ckt km respectively in 2000-01 fiscal year. At present there are 2314.5 ckt km of 230 kV line and 5533.6 ckt km of 132 kV line throughout Bangladesh under PGCB. PGCB has been implementing optical fiber network, that is OPGW parallel to its over head transmission lines to establish digital communication system to improve the control and monitoring of the transmission system. As by product this optical fiber network will be utilized for the telecommunication and IT network of the country and generate huge income for PGCB.
Government of Bangladesh decided to offload 25% of its shares i.e. a total of 91,08,940 Nos. of shares (Tk.100 each) through the Stock Exchanges under Direct Listing in order to bring public participation and more accountability on the company’s activities and to strengthen the capital market of the country. Accordingly PGCB was listed on October’ 2006 at Dhaka Stock Exchange (DSE) and Chittagong Stock Exchange (CSE). Offloading of shares started on October’ 2006. The Shares of the company has been trading in both Stock Exchanges since then.
ADB has provided financing for Meghnaghat Power Station Associated 230 kV Transmission Lines Project under the Ninth Power Project Loan. ADB has also provided another loan to PGCB under their Dhaka Power System Upgrade Project for construction of 50 km 230 kV transmission line and associated substation in the western part of Dhaka city, which enabled completion of a transmission line ring around Dhaka city. ADB has provided a separate loan to PGCB under their West Zone Power System Development Project for implementation of about 332 km long transmission lines and associated substations for improvement of transmission network in western grid. ADB has also financed the National Loan Despatch Centre Project.
However, later ADB has reallocated the savings from West Zone Power System Development Project to finance the project titled Shunt Compensation by capacitor Bank (Phase-1) and construction of a GIS Substation at Gallamari, Khulna. Very recently ADB has signed loan agreement to finance three new Transmission Projects of PGCB under their Sustainable Power Sector Development Program.
In addition to above, the other two projects titled “Bogra-Barapukuria 230 kV transmission line” and “Ishurdi-Baghabari 230 kV transmission line” are being constructed by CCC, China & Tata Power, India respectively under Supplier’s Credit Program. World Bank has expressed their willingness to finance a new project titled “Construction of Siddhirganj-Maniknagar 230 kV Transmission Line and associated substations”. The transmission structure of PGCB up to June-07 is as follows:
In 1990, an ordinance was issued, which was subsequently enacted as an Act transferring the 132 kv, 33 kv Transmission and distribution system in the Greater Dhaka Area including the Metropolitan City to a newly created Government agency called the Dhaka Electric supply Authority (DESA). This was done to lessen the administrative burden on BPDB,s management by relieving it of the burden of managing about 50 percent of the energy distribution in the entire country.
Further, As part of the "Reforms-Funding" linkage agreed between the donor partners and the Government, a large part to the funding was linked to redefining the franchise area of DESA and handing over of distribution networks outside Metropolitan Dhaka City to PBSs under REB, and formation of a corporatized Dhaka Electric Supply company (DESCO) which will initially take over part of the distribution network of DESA and ultimately take over all its assets. The formation of this company was seen as an essential step towards ‘corporatization and commercialization’ of the sector and to reduce the excessive inefficiency in the distribution network. Especially, The Dhaka area is the largest single distribution territory consuming about 50 percent of the total electricity sold in Bangladesh. DESA, which is the distribution agency for the Dhaka area has a poor performance record with respect to system losses and accounts receivables. Although the performance has improved considerable since 1992 on account of intensive monitoring, there is a limit to the gains that can be made and it is felt that further progress can be achieved on a sustainable basis only if there is a change in the business environment, both external and internal to the organization, which will enable introduction of more sophisticated control and management systems, and also organizational accountability.
The new company (DESCO) is being created as a public sector company, incorporated under the Companies Act 1994 as a subsidiary of DESA. However, in the future, shares of the company will be offered to the private sector, other power sector entities and the general public to make the DESCO's management more responsive to its consumers. DESCO incorporated under the Companies Act 1994 with its own Memorandum and Articles of Association. The company as a whole owned by Government of Bangladesh and DESA representing government by acquiring 100% shares. DESCO managed by a part time Board of Directors appointed by its shareholders, they are responsible for policy decisions. The Board of Directors appointed managing Director and two full time Directors and they were also members of the Board Directors after appointment.
The Bangladesh Rural Electrification (RE) Program was founded with a Presidential Ordinance in October 1977 that established the Rural Electrification Board (REB) as the semi-autonomous government agency reporting to the Ministry of Power Energy and Minerals Resources, which was responsible for electrifying rural Bangladesh. Since its inception, the purpose of the program has been to use electricity as a means of creating opportunities for improving agricultural production and enhancing socio-economic development in rural areas, whereby there would be improvements in the standard of living and quality of life for the rural people
Today there are 70 operating rural electric cooperatives called Palli Bidyuit Samity (PBS), which bring service to approximately 72,00,000 new connection being made and more than 14,000 kms of line being constructed each year. REB started functioning in early 1978 and conceived 1st project containing 13 PBS. After twenty eight years, the number of PBS now stands at 70. The followings table depicts the main features of rural electrification in Bangladesh as on April, 2008.
Main features of rural electrification in Bangladesh
Description |
Unit |
Number of RES organized |
70 |
Number of RES operating commercially |
70 |
Number of district under the program |
61 |
Number of Up-Zillas under the program |
433 |
Number of villages electrified |
47,050 |
Total distribution line constructed |
2,13,337 Km |
Total distribution line energized |
2,11,396 Km |
Total 33/11 KV sub-stations constructed and commissioned |
373 (305 Constructed by REB, 68 taken over from PDB & DESA) |
Installed Capacity of Sub-stations |
2704 MVA |
Total number of consumers |
72,66,107 |
Total number of irrigation pumps connected |
2,00,115 |
System Loss |
11.57%(cumulative),10.17% (Apr-08) |
Electricity Regulatory Commission Act 2003 (Act No. 13 of 2003) was passed in the parliament in March 2003 for the establishment of as independent and impartial regulatory commission to regulate Electricity, gas and petroleum sector.
In April 2004, Regulatory Commission was established and started functioning. The mandate of the commission includes framing rules and regulation to ensure transparency in the management, operation and tariff determination in Electricity, gas and petroleum sector. The commission will protect consumer and industry interest and promote competitive market. Major functions of BERC are as follows:
Apart for this the BERC has enacted the Licensing regulation for generation in 2006 and BERC is in the final phase of enacting Electricity Transmission Regulation, 2008 and Electricity Distribution Regulation, 2008.
Milestones of Electricity Supply in Bangladesh
Year |
Description |
1948 |
Electricity Directorate created in order to plan and develop power supply situation of the country. |
1959 |
Water and Power Development Authority (WAPDA) was created. |
1960 |
Electricity Directorate was merged with Water and Power Development Authority. |
1966 |
Ashuganj Power Station (724MW), the second largest power station in Bangladesh, established with the financial assistance of German Government. |
1972 |
WAPDA was bifurcated into two autonomous Boards under an Ordinance (P.O. 59 of 1972). |
1972-73 |
A rehabilitation and development programme was undertaken in the First Five Year Plan |
1972 |
Bangladesh Power Development Board, established as the authority for planning, construction and operation of power generation and transmission facilities throughout Bangladesh and for distribution in urban areas except metropolitan city of Dhaka and its adjoining area. |
October 1977 |
The Bangladesh Rural Electrification (RE) Program was founded with a Presidential Ordinance that established the Rural Electrification Board (REB) as the semi-autonomous government agency reporting to the Ministry of Power Energy and Minerals Resources. This marked the start of Power sector reforms. |
Early 1978 |
REB started functioning and conceived 1st project containing 13 Palli Bidyut Samities (PBS) |
1991 |
Dhaka Electricity State Authority created. |
1993 |
A high power inter-ministerial Committee on 'Power Sector Reform` was constituted in 1993. |
1995 |
Power Cell, created under Ministry of Energy & Mineral Resources in 1995 to drive power sector reforms and to promote private power development. |
1996 |
Power generation and distribution was opened to both local and foreign private investments with the formulation of "The Private Sector Power Generation Policy" in 1996. |
1996 |
The National Energy Policy adopted in 1996. |
November 1996 |
Dhaka Electric Supply Company Limited (DESCO) was incorporated in November 1996 with ultimate objective of taking over all assets from DESA. |
November 21, 1996 |
Power Grid Company Limited of Bangladesh (PGCB) was incorporated on 21 November 1996 to take over entire transmission assets of BPDB and DESA by December 2002. |
March 25, 1998 |
Power Division was established in 1998 under the Ministry of Power, Energy and Mineral Resources vide Cabinet Division Notification No. CD-4/1/94-Rules/23(100), dated 25 March 1998 |
1998 |
Dhaka Electric Supply Authority (DESA) under the DESA Act as amended in 1998 was restructured into a corporate body with an independent Board of Directors. |
September 1, 1998 |
DESCO commenced commercial operation from 1 September 1998 by taking over Mirpur area from DESA. |
1998 |
GOB approved “Policy Guideline for Small Power Plant (SPP) in Private Sector” in 1998 |
June 2000 |
Vision Statement and Policy Statement on Power Sector Reforms released. |
December 2002 |
Transmission assets of DESA (other than those that form integral part of DESA operation) handed over to PGCB. |
March 10, 2003 |
Integrated bill cleared by the parliament on 10 March 2003 which led to the formulation of Bangladesh Electricity Regulatory Commission. |
April 2004 |
Regulatory Commission was established and started functioning. |
December 31, 2003 |
PGCB completed taking over of all the transmission assets and operating them. |
January 2004 |
GOB approved conversion of BPDB into a holding company. |
October 2006 |
PGCB was listed on October’ 2006 at Dhaka Stock Exchange (DSE) and Chittagong Stock Exchange (CSE). |
2006 |
BERC enacted the Licensing regulation for generation. |
Reforms and Restructuring: Measures Undertaken
The foremost priority in the Power sector reform agenda of the Government is to establish a legal frame-work for enabling business transaction in the new environment. The roles of owners and operators is being delegated to evolving functional entities according to the structural needs of reformed power sector under the supervision of the Energy Regulatory Commission. Government shall, however, issue policy directives on matters concerning electricity including on measures which are considered necessary for the overall planning and coordination for the development of the electricity sector.
In fact power sector reforms started in late '70s through the creation of Rural Electrification Board (REB). However as part of reform programs following activities have been done so far:
Generation:
Transmission:
Distribution:
Renewable Energy Development:
Tariff
The 3-year Road Map (2008-2010) including the time-bound action plan has been envisaged in line with Poverty reduction Strategy Paper (PRSP) for realization of the vision of reaching electricity to all by 2020. Six monthly rolling goals for the next three years were also prepared (Annexure - II).
During this period, electricity demand is expected to grow at the rate of 8-10% per annum. As such, the demand is expected to rise to about 6,608 MW by 2010. Therefore for reliable supply of power, the generation capacity will be required to be raised to at least 8,000 MW which will facilitate raising the per capita consumption to 172 KWh and access to electricity to 60%. Thus about 2,800 MW of new generation capacity will be needed to ensure adequate supply of electricity. Simultaneously, about 2200 circuit km (100 km 400 kV, 1500 km 230 kV and 600 km 132 kV) of transmission line and about 50,000 km of distribution line will have to be constructed for evacuation and distribution of power.
Together with institutional reform and prudent investment program ensuring least cost solution can provide quantity and quality power to the consumers at an affordable price for sustainable economic and social development of the country. However, in order to redress the sufferings of the consumers due to acute power shortage in the shortest possible time, the Government has, as an interim measure, contracted with private power companies for generation and supply of electricity to BPDB on rental basis for 3 years. These rental power plants (about 300 MW) are expected to be commissioned within 4 months of signing of contract i.e., by May 2008. It is expected that within next 3-4 years, the power plants planned for implementation according to least cost plan will come on line, when these rental power plants will not be required. In response to overall gas situation, particularly transmission and distribution constraints new base load, small IPPs and rental power plants are being set up in and around areas where reliable gas supply is available.
The primary objective of the 3-year institutional reform programme is to create an institutional foundation on which to ramp, in a sustainable manner, the substantial investments needed for the sector to properly support economic growth and reduce poverty. This will require the sector to be restructured to improve its efficiency, transparency and overall governance, facilitate effective and independent regulation, expand competition, and begin to improve the quality of electricity services.
Experience gained from the reform attempts has been considered in preparing the road map. Creation of DESA as a separate authority, without introducing new management & corporate culture and without sufficient autonomy & incentive, did not yield good results. Again creation of Ashuganj Power Station Company Ltd (APSCL) and WZPDC without sufficient preparatory works and addressing governance & employee issues properly created mismanagement in the business. Implementation of road map in future will be based on in-depth study.
The main outcomes being sought over the next 3-years is further unbundling of electricity supply into an economically viable number of separate generation and distribution companies, and a single transmission company. These operating companies will act as subsidiaries of BPDB holding company. Technical co-ordination of power system operation will be enhanced through implementation of National Load Dispatch Centre (NLDC) project linking generation and grid substations. A strong planning and power trading department for bulk power management will be organized under the BPDB holding company. The indicative milestones for the institutional reforms of the power sector for the next 3 years are summarized below:
i. Generation:
i.a. Existing Generation:
1.1. All the existing power stations in the public sector will be converted into profit centres for eventual conversion to a corporatized entity individually or on cluster basis which will be retained by BPDB holding company.
1.2. All commercial issues related to asset transfer and valuation will be completed.
1.3. The business and financial plans will be developed.
1.4. All works related to employee issues including payment of service benefits will be completed as per guidelines provided in the Policy Statement on power sector reforms. Employment of all employees to the corporatized entities shall be governed by the latter’s service rules.
1.5. All efforts will be undertaken by GOB so that the emerging entities can start functioning commercially.
1.6. Special plans will be developed to enhance technical and managerial efficiencies and establishing good governance.
1.7. Special attention will be given to Human Resources Development (HRD) program.
1.8. To improve technical and management capability and to establish accountability, special organizational activities like TQM will be introduced.
ii.b. New Generation:
New generation projects will be taken up to achieve the desired security of supply at generation level to be met at least cost and generation capacity will be sought through a mix of sources i.e. public, private, and public-private joint ventures. Employment of Private Sector resources in new generation will be encouraged. For public sector new generation, special attention will be given to good governance, efficient O&M and establishing commercial environment.
ii. Transmission:
1. PGCB will continue to operate as a wheeler of electricity.
2. Special attention will be given to Human Resources Development (HRD) program.
3. Demarcation of functional area of generation, transmission and distribution will be finalized and installation of system metering will be completed to establish commercial arrangement among the sector entities.
iii. Distribution:
It is realized that main problem lies in the distribution segment. Therefore the success of the reform programmes can not be sustained until commercial environment is established in this segment.
iii.a. BPDB:
1. BPDB distribution segment will be converted into a number of distribution companies under BPDB holding company. All works towards corporatization of BPDB distribution will be completed.
2. All commercial issues related to asset transfer and valuation will be completed.
3. Business and financial plans will be developed.
4. All works related to employee issues including payment of service benefits will be completed as per guidelines provided in the Policy Statement on power sector reforms. Employment of all employees to the corporatized entities shall be governed by the latter’s service rules.
5. All efforts will be undertaken to complete computerization of commercial functions to boost revenue collection and establishing transparent transaction.
6. Special attention will be given to Human Resources Development (HRD) program.
iii.b. DESA/DPDC:
1. DPDC will be fully functional with employees recruited through a process approved by the company.
2. All commercial issues related to asset transfer and valuation will be completed.
3. Business and financial plans will be developed.
4. All works related to employee issues including payment of service benefits will be completed as per guidelines provided in the Policy Statement on power sector reforms. Employment of all employees to the corporatized entities shall be governed by the latter’s service rules.
5. All commercial functions will be computerized to boost revenue collection and improve transparency.
6. Special attention will be given to Human Resources Development (HRD) program.
iii.c. REB:
1. Steps will be taken to improve REB’s performance based on reorganization study.
2. Steps will be taken to improve network expansion planning process using advanced tools (software) for least cost option in line with GOB’s vision to provide access to electricity to people at an affordable cost.
iv. Sector Regulation:
The Bangladesh Energy Regulatory Commission Act was enacted in March 2003 and
Bangladesh Energy Regulatory Commission has been made functional since April 2004. The Commission has mandate to regulate the electricity, gas and petroleum sector. The Commission already issued ‘generation licensing regulation’ in 2006. Government recently approved service regulations of BERC staff. The Commission will be fully functional by the year 2008, with appointment of qualified staffs pursuant to the approved BERC organogram.
v. Power Market Structure:
At present BPDB is functioning as Single Buyer and it will continue functioning except for some direct power purchase from small power producers by the utility. Multi buyer/Competitive pool may be adopted when the market becomes mature and stable.
vi. Implementation and Monitoring Approach of Reform Program:
Implementation of the reform program is a very complicated and difficult task and requires well-organized, integrated and comprehensive plan and actions. It will require close co-ordination, interaction and strong commitment of the Government, and other stakeholders. A high level National Steering Committee has been formed. A Task Force has also been established and a Working Group has been formed in each utility to implement and monitor the power sector reform programs in a coordinated and comprehensive manner.
The Government is giving its best effort to reach the goal of providing electricity service to all the people by the year 2020. Along with the reform program, Government has taken a number of time bound development plan. By the year 2020, installed capacity has been planned to increase to 17,765 MW. On the other hand, as per this plan transmission line will be increased to 8,396 KM and distribution line will be extended to 4,77,558 KM. In order to implement this plan investment required is 3 billion US$ upto the year 2007 and 4.5 billion US$ and 7.0 billion US$ during 2007-2012 and 2012-2020 time period respectively. Along with the own financing of the Government, assistance from the development partners and private investors are required to bear this huge expense. A summary of the development plan is given below:
Power System Development Plan up to 2020
Sl. No. |
Item |
Year |
New Addition |
|||
2004 |
2007 |
2012 |
2020 |
|||
1 |
Installed Capacity, MW |
4,710 |
6,441 |
9,666 |
17,765 |
14,525 |
2 |
Peak Demand, MW |
3,622 |
5,368 |
7,887 |
14,600 |
10,978 |
3 |
Net Generation, MKWh |
20,302 |
26,651 |
39,157 |
76,545 |
56,243 |
4 |
Transmission Line, Km |
3,919 |
4,898 |
7,180 |
8,396 |
4,477 |
5 |
Capacity of Grid S/S,MVA |
|
|
|
|
|
|
(a) 230/132 kV |
3,700 |
5,950 |
11,575 |
19,075 |
15,375 |
|
(b) 132/33 kV |
7,084 |
9,642 |
17,920 |
27,367 |
20,283 |
6 |
Distribution Line, Km |
2,26,232 |
2,66,375 |
3,45,530 |
4,77,558 |
2,51,326 |
7 |
Nos. of Consumers, Lac |
79.6 |
90.36 |
127.55 |
207.67 |
128.07 |
8 |
Nos. of Village Electrified |
44,546 |
52,071 |
69,571 |
84,000 |
39,454 |
9 |
Per Capita Generation, kWh |
155 |
190 |
260 |
450 |
295 |
10 |
Access to Electricity |
35% |
47% |
65% |
100% |
65% |
11 |
Investment Requirement, (10 US$) |
|
3.0 (upto 2007) |
4.5 (1207-2012) |
7.0 (2012-2020) |
|
Government is committed for providing affordable and reliable electricity to all citizens by 2020 for economic and social development. To materialize this vision, power sector reform, restructuring and private sector participation is utmost important for introducing competition, performance improvement and growth. A number of steps have been identified in generation, transmission and distribution sub-sector for structural reform and competitive energy market which have been mentioned below.
Generation:
Transmission:
Distribution:
Industry & Market Structure:
Fiscal incentives
Other facilities and incentives for foreign investors
Year wise Targets
Year 2008 (January to December)
Year 2009 (January to December)
Year 2010 (January to December)